ITEM TITLE:  
2019 2nd Quarter Projects Report
SUBMITTED BY: Nathan Duval, Capital Facilities Director
 
FISCAL NOTES:  
Expenditure Required: N/A
Unencumbered Balance: N/A
Funding Source: N/A
 
RECOMMENDATION:
Receive & File
SUMMARY STATEMENT:
The attached report provides a summarized picture of current projects. Some points of note include:
•                     Report only lists projects with significant measurable work within 2019
•                     Projects/maintenance items less than $20,000 were generally not included
•                     Significant project impacts to schedule resultant from backlog at State Fire Marshal office
•                     Significant project impacts to schedule resultant from earthquake demands on design firms
•                     Average COV project change order rate 2-4% including some significant outliers
o                     0-10% acceptable/expected
o                     11-20% acceptable based on significant discovery or scope change
o                     21%+ significant change, requires investigation/lessons learned
•                     Capital Facilities Department fully staffed as of July 2019 with Meridian acting as consultant CM on both field and design projects.