ITEM TITLE:
Approval of Contract Amendment #2 with Kinney Engineering, LLC on Pavement Management Phase II - West Hanagita Street and Ptarmigan Place in the amount of $591,193.16
SUBMITTED BY: Brad Sontag Capital Facilities Project Manager
FISCAL NOTES:
Expenditure Required: $591,193.16
Unencumbered Balance: $3,416,555.47
Funding Source: 310-1110-58000
RECOMMENDATION:
Approve Contract Amendment #2 with Kinney Engineering, LLC on Pavement Management Phase II - West Hanagita Street and Ptarmigan Place in the amount of $591,193.16
SUMMARY STATEMENT:
Project Description: The intent of this contract amendment is to provide Construction Management Services for Pavement Management Phase II - West Hanagita Street and Ptarmigan Place. The services will include the following: on-site construction inspection, material testing and management tasks for the duration of the project.
This scope was not included in the original contract amount. We waited until the projects were approved and the scope and contractors were finalized.
PTS and Alaska Test Labs are the subcontractors that will perform the on site work; they completed these same services for the City last year for Phase I.