File #: 21-0069    Version: 1
Type: Report Status: Filed
File created: 1/27/2021 In control: City Council
On agenda: 2/16/2021 Final action: 2/16/2021
Title: Change Order Report: Change Order No. 1 with KC Corporation for Animal Shelter Incinerator Replacement Project
Attachments: 1. Executed - Animal Shelter Incinerator Replacement - CO #1, 2. Animal Shelter Incinerator Replacement - Change Order Log

ITEM TITLE: 

Change Order Report: Change Order No. 1 with KC Corporation for Animal Shelter Incinerator Replacement Project

 

SUBMITTED BY: Melissa Ross, Capital Facilities Project Manager

 

FISCAL NOTES: 

Expenditure Required: $16,816.00

Unencumbered Balance: $26,485.40

Funding Source: 350-0310-55000.2002

 

RECOMMENDATION:

Receive and File

 

SUMMARY STATEMENT:

The project scope includes the replacement of the processing station in addition to the incinerator. The intent was to reuse the actual processor component. The current processor is not compatible with the new processing station, so a new processor was required to be purchased to make the new unit functional.

Due to shipping times being increased because of COVID the substantial completion date was extended to May 01, 2021.

 

This report is filed per City Procurement Code 2.80.050.