File #: 21-0096    Version: 1
Type: New Business Status: Passed
File created: 2/4/2021 In control: City Council
On agenda: 2/16/2021 Final action: 2/16/2021
Title: Approval of a Contract with Wolverine Supply, Inc. for the Valdez Elementary & High School Water Piping Replacement in the amount of $1,169,000.00.
Attachments: 1. Valdez Elementary and High School Water Piping Replacement - Bid Summary, 2. Valdez Elementary & High School Water Piping Replacement - Bid Package, 3. Specifications, 4. 100% HHES Domestic Water Piping Replacement Construction Document 12-01-20, 5. 100% VHS Domestic Water Piping Replacement Construction Document 12-01-20
ITEM TITLE:
title
Approval of a Contract with Wolverine Supply, Inc. for the Valdez Elementary & High School Water Piping Replacement in the amount of $1,169,000.00.
body
SUBMITTED BY: Scott Benda, Senior Project Manager

FISCAL NOTES:
Expenditure Required: $1,169,000.00
Unencumbered Balance: $3,500,000.00
Funding Source: 350-0310-55000.1809 & 350-0310-55000.1810

RECOMMENDATION:
rec
Approve the Contract with Wolverine Supply, Inc. for the Valdez Elementary & High School Water Piping Replacement in the amount of $1,169,000.00.

end
SUMMARY STATEMENT:
The Valdez Elementary & High School Water Piping Replacement project was out to bid for fifty days and three (3) bids were submitted. Wolverine Supply, Inc., of Wasilla submitted the low bid of $1,169,000. The project consists replacing the domestic cold water, hot water and hot water recirculation piping in the elementary and high school buildings. Piping will be replaced to the existing fixtures where access to piping is available. Where access to piping is not possible, piping will be connected to existing branch piping with isolation valves or routed to the fixture.

The need for replacement is due to the original galvanized steel water piping rusting internally causing very bad water quality and suffering from numerous leaks over the years. It is important to note that this project will not replace the existing water piping located within the walls servicing the existing fixtures. That work will be addressed in future remodeling projects. This project will result in improved water quality at both schools and the elimination of above the ceiling leaks due to rusted out piping.

Construction is scheduled to begin on May 22nd and to be substantially complete by August 1, 2021.
Wolverine Supply and their subcontractor Valley Mechanical have years of experience working within both of the schools and are very familiar with the facilities, staff and unique circumstances of completing a large project during ...