Change order #4 on the Pavement Management Phase 1 - West Egan Drive Project documents several adjustments in bid item quantities and the resulting changes in the overall project cost. These adjustments are as follows:
WE-1 quantity reduced by 375 CY
WE-2 quantity reduced by 600 TON
WE-3 quantity increased by 750 TON
WE-20 quantity reduced by 1 EA
WE-22 quantity increased by 19 EA
WE-32 quantity reduced by 19 EA
WE-41 increased by 45 LF
The aggregate cost adjustment for these quantity changes is an increase of $25,500.00