File #: 20-0297    Version: 1
Type: Report Status: Filed
File created: 7/1/2020 In control: City Council
On agenda: 7/7/2020 Final action: 7/7/2020
Title: Change Order Report: Contract with Harris Sand & Gravel for Pavement Management Phase 1 - West Egan Drive.
Attachments: 1. Pavement Management Phase 1 - West Egan Drive: Change Order #1

ITEM TITLE: 

Change Order Report: Contract with Harris Sand & Gravel for Pavement Management Phase 1 - West Egan Drive.

SUBMITTED BY: Thomas Sanborn, Capital Facilities Project Manager

 

FISCAL NOTES: 

Expenditure Required: $17,892.00

Unencumbered Balance: $4,814,668.65

Funding Source: 310-1200-58000

 

RECOMMENDATION:

Receive & File

SUMMARY STATEMENT:

Change Order 1 adds the replacement of a 12-inch water main valve and deducts the work for a 6-inch water valve replacement from the contract.  This need was clarified by the City of Valdez Water Department following a site walkthrough.

The total cost for this change order, included deductive savings, is $17,892.

This report is filed per City Procurement Code 2.80.050