File #: 20-0258    Version: 1
Type: Report Status: Filed
File created: 6/10/2020 In control: City Council
On agenda: 6/16/2020 Final action: 6/16/2020
Title: Change Order Report: Contract Amendment with Cornerstone General Contracting, Inc. for the Providence Valdez Medical Center Copper Pipe Replacement.
Attachments: 1. Executed - Providence Valdez Medical Center Copper Pipe Replacement - Construction CO 1, 2. Providence Valdez Medical Center Copper Pipe Replacement - Change Order Log

ITEM TITLE: 

Change Order Report: Contract Amendment with Cornerstone General Contracting, Inc. for the Providence Valdez Medical Center Copper Pipe Replacement.

SUBMITTED BY: Tom Sanborn, Capital Facilities Project Manager

 

FISCAL NOTES: 

Expenditure Required: $38,896.00

Unencumbered Balance: $44,680.45

Funding Source: 315-0310-58000.9197

 

RECOMMENDATION:

Receive and File.

SUMMARY STATEMENT:

An active water leak was discovered during construction. This change order covers the corrective action and necessary repairs that resulted from this leak. The cost is in excess of the built-in contract contingency but can be covered within the overall project budget.

The project is back under construction following a COVID related pause and work continues at the Clinic. Completion anticipated end of June early July.

 

This Report is filed per City Procurement Code 2.80.050.