File #: 20-0039    Version: 1
Type: New Business Status: Passed
File created: 1/9/2020 In control: City Council
On agenda: 1/21/2020 Final action: 1/21/2020
Title: Approval of Contract Award to Orion Construction Inc. for the Fire Station 1 Hazmat Remediation and Ventilation Upgrades Project in the Amount of $271,500.00
Attachments: 1. Fire Station1 Hazmat Remediation and Ventiliation Upgrades - Bid Summary, 2. Fire Station 1 Hazmat Remediation and Ventilation Upgrades - Complete Contract
ITEM TITLE:
title
Approval of Contract Award to Orion Construction Inc. for the Fire Station 1 Hazmat Remediation and Ventilation Upgrades Project in the Amount of $271,500.00

body
SUBMITTED BY: Brad Sontag, Capital Facilities Project Manager

FISCAL NOTES:
Expenditure Required: $271,500.00
Unencumbered Balance: $309,604.00
Funding Source: 350-0310-55000.1605

RECOMMENDATION:
rec
Approve the Construction Contract with Orion Construction Inc. in the Amount of $271,500.00 for the Fire Station 1 Hazmat Remediation and Ventilation Upgrades Project.

end
SUMMARY STATEMENT:
Project Description: The project scope consists of:
? Remediation of known and suspected mold contamination in wall and ceiling assemblies in decontamination room and adjoining spaces.
? Remediation of known and suspected materials containing asbestos in areas of work.
? Demolition of affected finishes and assemblies as required.
? Patch/repair/replace assemblies and finishes, as required, in areas of remediation and other work.
? Replace existing HRV in decontamination room.
? Provide and install new HRV to serve residential dormitory.
? Implement recommendations to improve ventilation from existing AHU-1.
? Implement recommendations to improve monitoring and evacuation of vehicle exhaust in apparatus bays 1, 2, and 3.
See attached drawings and specifications for further scope of work.
?Additive Alternate #1 - Provide and install a Vehicle Exhaust Capture system in apparatus bays 4 and 5.

See attached drawings and specifications for further scope of work.

The exhaust capture system is designed to be relocated to other facilities, if needed, once the new station is complete.

This project timeline was moved up to level department resources over the summer construction season.

Construction Schedule: Project to begin tentatively in mid-February 2020. Actual start date will be determined by the lead time of materials needed for this project. All work shall be completed in accordan...

Click here for full text