ITEM TITLE:
Procurement Report: Professional Services Agreement with RSA Engineering, Inc. VHS Generator Replacement - Design
SUBMITTED BY: Thomas Sanborn, Capital Facilities Project Manager
FISCAL NOTES:
Expenditure Required: $42,506
Unencumbered Balance: $75,000
Funding Source: 350-0310-55000.1808
RECOMMENDATION:
Receive & File
SUMMARY STATEMENT:
Project Description: This is the design contract to replace the backup generator at Valdez High School.
Schedule: The Contractor has 90 days from the date of the Notice to Proceed to deliver the completed design.
This report is filed per City Procurement Code 2.80.040 (procurement) 2.80.050 (change orders and contract amendments).