File #: 19-0390    Version: 1
Type: Report Status: Filed
File created: 9/6/2019 In control: City Council
On agenda: 9/17/2019 Final action: 9/17/2019
Title: Change Order Report: Change Order No. 3 with Prosser-Dagg Construction for the VHS Concrete Replacement Project.
Attachments: 1. Executed VHS Concrete Replacement - CO #3, 2. VHS Concrete Replacement- Change Order Log

ITEM TITLE: 

Change Order Report: Change Order No. 3 with Prosser-Dagg Construction for the VHS Concrete Replacement Project.

 

SUBMITTED BY: Melissa Ross, Capital Facilities Project Manager

 

FISCAL NOTES: 

Expenditure Required: $27,663.18

Unencumbered Balance: $877.27

Funding Source: 350-0310-55000.1806

 

RECOMMENDATION:

Receive and File

 

SUMMARY STATEMENT:

Estimated quantities for Change Order #2 were established prior to completion of demolition of the parking lot. The project required more materials for leveling course and subgrade because of as-found conditions that weren’t accounted for during the original design. Other minor adjustments to unit price quantities are included with this change order. This is the final change order on the contract and the project is financially complete.

This report is filed per City Procurement Code 2.80.050.