The attached report provides a summarized picture of current projects. Some points of note include:

                     Report only lists projects with significant measurable work within 2019

                     Projects/maintenance items less than $20,000 were generally not included

                     Significant project impacts to schedule resultant from backlog at State Fire Marshal office

                     Significant project impacts to schedule resultant from earthquake demands on design firms

                     Average COV project change order rate 2-4% including some significant outliers

o                     0-10% acceptable/expected

o                     11-20% acceptable based on significant discovery or scope change

o                     21%+ significant change, requires investigation/lessons learned

                     Capital Facilities Department fully staffed as of July 2019 with Meridian acting as consultant CM on both field and design projects.