File #: 18-0331    Version: 1
Type: Report Status: Filed
File created: 9/26/2018 In control: City Council
On agenda: 10/2/2018 Final action: 10/2/2018
Title: Change Order Report: Pacific Pile and Marine, LP for Phase 2 New Harbor Development Upland Facilities and Inner Harbor Facilities in the Amount of $31,900.77
Attachments: 1. Executed - Phase 2 New Harbor Development Upland Facilities and Inner Harbor Facilities - CO # 14, 2. Phase 2 New Harbor Development Upland Facilities and Inner Harbor Facilities - CO Log

ITEM TITLE: 

Change Order Report:  Pacific Pile and Marine, LP for Phase 2 New Harbor Development Upland Facilities and Inner Harbor Facilities in the Amount of $31,900.77

 

SUBMITTED BY: Nathan Duval, Capital Facilities Director

 

FISCAL NOTES: 

Expenditure Required: $31,900.77

Unencumbered Balance: $350,160.78

Funding Source: 310-6450-58010 - New Harbor GO 2015

 

RECOMMENDATION:

Receive and File.

SUMMARY STATEMENT:

Additional upgrades were required to install owner-furnished commercial grade washers and dryers as well as install token operated devices.