Title: Approval of Change Order #4 with F & W Construction Company, Inc., for the Kelsey Dock Interpretive Center Phase I Project in the Amount of $56,125.64
Attachments: 1. Kelsey Dock Interpretive Center - Phase 1 - CO # 4, 2. Kelsey Dock Interpretive Center - Phase I - Change Order Log, 3. Kelsey RFP-04A Heat Strip Heaters 08.20.18

ITEM TITLE: 

Approval of Change Order #4 with F & W Construction Company, Inc., for the Kelsey Dock Interpretive Center Phase I Project in the Amount of $56,125.64

 

SUBMITTED BY: Nathan Duval, Capital Facilities Director

 

FISCAL NOTES: 

Expenditure Required: $56,125.64

Unencumbered Balance: $410,329.81

Funding Source: 312-6400-58000 City Contribution Exp.

 

RECOMMENDATION:

Approve Change Order #4 with F & W Construction Company, Inc., for the Kelsey Dock Interpretive Center - Phase I project in the Amount of $56,125.64.

 

SUMMARY STATEMENT:

The Port requested the option of installing heaters in the Kelsey Dock canopy.  Attached is a proposal from F & W Construction, Inc. to assist with a design build effort to install said heaters.  The install cost is approximately $56,000.00 with an additional approximately $10,000.00 in design.  A deductive change order is in process for value engineering the utility routing to help offset some of this cost.