File #: 17-0293    Version: 1
Type: Report Status: Filed
File created: 5/25/2017 In control: City Council
On agenda: 6/6/2017 Final action: 6/6/2017
Title: Whalen Avenue Construction
ITEM TITLE:
title
Whalen Avenue Construction
body
SUBMITTED BY: Todd Wegner, Asst. City Manager

FISCAL NOTES:
Expenditure Required: N/A
Unencumbered Balance: $284,258
Funding Source: 310-8165-58000

RECOMMENDATION:
rec
Receive and file
end
SUMMARY STATEMENT:
Capital Facilities would like to recommend construction of Whalen be postponed until 2018 or beyond.
1. Developing Whalen started as a conversation between the City and Edison Chouest. Perhaps at that time it may have been necessary to develop the road if driveways were connecting to Whalen. However, the final subdivision plans show all driveways entering onto the future cul-de-sac, not onto Whalen.
2. The utility infrastructure that will go beneath Whalen has not yet been thoroughly vetted.
a. The discussion around the future well at the corner of Whalen and Pioneer is still ongoing. A waterline for the well could be installed in anticipation of, but even so the location of the new well has not yet been finalized. That leaves a chance the well waterline may not get used if the well is relocated.
b. The City is currently planning on looping the potable waterline with one stub out to the empty lot owned by Port Valdez on the west side of Whalen. No development of this property is known yet. By postponing the design, it increases the chance a plan might arise in which case the City could stub out accordingly.
3. The current unencumbered balance is far below the engineer's cost estimate, a difference of $542,192. If the City Council would like to move forward, this is the amount that would be requested. The account to transfer this from is unknown.
4. Whalen is currently designed from Egan to Pioneer. It will remain as a dirt road from Pioneer to Klutina. If the project is postponed until the above issues are resolved it would be recommended to extend the redevelopment of Whalen all the way from Egan to Klutina. In this case, you are connecting a much higher level of residents to the main st...

Click here for full text