File #: 17-0291    Version: 1
Type: Unfinished Business Status: Filed
File created: 6/1/2017 In control: City Council
On agenda: 7/5/2017 Final action: 7/5/2017
Title: Approval of Contract Award to Harris Sand & Gravel for the Lowe River Slope Improvements Project in the Amount of $51,200. Postponed from the Regular Meeting on June 20, 2017.
Attachments: 1. Lowe River Slope Improvements - Bid Summary.pdf, 2. Lowe River Slope Improvements Plans 05032017, 3. Lowe River slope improvements aerial photos

ITEM TITLE: 

Approval of Contract Award to Harris Sand & Gravel for the Lowe River Slope Improvements Project in the Amount of $51,200. Postponed from the Regular Meeting on June 20, 2017.

 

SUBMITTED BY: Scott Benda, Capital Facilities Project Manager II

 

FISCAL NOTES: 

Expenditure Required: $51,200

Unencumbered Balance: $1,441,383

Funding Source: 310-8060-58000

 

RECOMMENDATION:

Mayor Knight will provide an update from the Flood Task Force Meeting on June 27, 2017. 

 

 

SUMMARY STATEMENT:

Project Description: Provide and install 400 CY of class III riprap to groin 4 in Alpine Woods. This project will reinforce a section of an existing dike that was installed last summer under an emergency declaration to divert high water from the Lowe River from entering into the lower end of Alpine Woods subdivision. The dike is vulnerable to erosion if additional riprap is not put in place.

Construction Schedule: The work will be completed with 30 days

Liquidated Damages: $1000 per day

Bidding: Length of bid period was 15 days. One bid was received.

Engineer’s Estimate: $50,000

Design Review Stakeholders: Capital Facilities, Pubic Works, ComDev, DOWL Engineering