File #: 17-0221    Version: 1
Type: New Business Status: Passed
File created: 4/21/2017 In control: City Council
On agenda: 4/25/2017 Final action: 4/25/2017
Title: Approval of Contract Award to Pacific Pile & Marine for Phase 2 of the Valdez New Boat Harbor Project in the Amount of $24,907,321
Attachments: 1. New Harbor Development Phase 2 - Construction Contract Bid - Body, 2. Inner Harbor Facilities, 3. Upland Facilities, 4. New Harbor Development Phase 2 - BIDSUMMARY
ITEM TITLE:

title
Approval of Contract Award to Pacific Pile & Marine for Phase 2 of the Valdez New Boat Harbor Project in the Amount of $24,907,321

body
SUBMITTED BY: Jason Miles, PE, Capital Facilities Director

FISCAL NOTES:
Expenditure Required: $24,907,321
Unencumbered Balance: $31,373,573
Funding Source: 310-6450-49545 (grant)
310-6450-58000

RECOMMENDATION:
rec
Approve a construction contract to Pacific Pile & Marine in the amount of $24,907,321 for Phase 2 of the Valdez New Boat Harbor project.

end
SUMMARY STATEMENT:

Project Description: Phase 2 entails construction of the upland facilities to include restrooms, the Harbormaster warehouse, a state-of-the-art bilge water treatment facility, and site paving. Phase 2 also entails construction of the inner harbor facilities to include the floating docks, gangways, drive down ramp and float, in-water rock removal, and a sediment berm. This work coincides with completion of the Corps of Engineers portion of the new harbor development which includes the basin dredging and breakwater construction. Select plan sheets are attached to provide a graphic understanding of the work included with Phase 2.
Construction Schedule: Project to start upon award of the contract. Completion Milestone Dates, as required by contract:
1. Uplands Facilities (Schedule A) shall be substantially complete, including completion of as-built survey no later than 9/30/2018.
2. Uplands Facilities (Schedule A) shall be complete, including completion of punch list items and submittal of associated survey and close out documents (Final Acceptance) on or before 11/1/2018.
3. All in-water work shall be complete and gangways and moorage floats installed an available for vessel moorage and pedestrian access (not including utilities service) on or before 5/1/2019.
4. Inner Harbor Facilities (Schedule B) shall be substantially complete, including installation of utilities on or before 7/15/2019.
5. Inner Harbor Facilities (Schedule B...