Title: Change Order Report: Contract with Orion Construction, Inc. for HHES and VHS Generator Replacement
Attachments: 1. Executed CO #9 - Hermon Hutchens Elementary (HHES) and Valdez High School (VHS) Generator Replacement, 2. Change Order Log

ITEM TITLE: 

Change Order Report: Contract with Orion Construction, Inc. for HHES and VHS Generator Replacement

SUBMITTED BY: Tom Sanborn

 

FISCAL NOTES: 

Expenditure Required: $35,278.87

Unencumbered Balance: $42,237.03

Funding Source: 350-0310-55000.1808

 

RECOMMENDATION:

Receive & file

SUMMARY STATEMENT:

Change Order #9 will replace all currently installed DDC equipment with Meridian Systems equipment at the new VHS/GMS generator. The currently installed equipment is a separate proprietary system from the HVAC controls at GMS, making these systems are unable to communicate.  It is necessary for these systems to communicate in order for the proper HVAC limits to run while the generator is providing power to the facility.

This report is filed per City Procurement Code 2.80.050