ITEM TITLE:
title
Approval of Preliminary Plat for ASLS 2017-66. Applicant - State of Alaska Department of Natural Resources, Division of Mining Land and Water. A Depiction of ADL 232974.
body
SUBMITTED BY: Paul Nylund - Senior Planner/GIS Technician
FISCAL NOTES:
Expenditure Required: N/A
Unencumbered Balance: N/A
Funding Source: N/A
RECOMMENDATION:
rec
Approve Preliminary Plat for ASLS 2017-66.
end
SUMMARY STATEMENT:
The State of Alaska Department of Natural Resources, Division of Land and Water, has applied for a subdivision within Protracted Sections 17, 19, 20, 29 & 30 of Tract A, Township 9 South, Range 6 West, Copper River Meridian, Alaska, Valdez Recording District. This survey, known as ASLS-2017-66, is also being concurrently reviewed by the AK DNR Survey Section as ADL #232974.
Randal H Brinker, of R & M Consultants, Inc., is the surveyor on this project. Gwen Gervelis, the Chief of the Survey Section of the State of Alaska Department of Natural Resources, Division of Land and Water, is the signatory on this subdivision.
This survey represents a private non-exclusive access easement encompassing the facilities of the Allison Creek Hydroelectric System, including the dam, penstock, power plant, access road and transmission line. The survey work has been completed.
Randal H Brinker, of R & M Consultants, Inc., is the surveyor on this project. Gwen Gervelis, the Chief of the Survey Section of the State of Alaska Department of Natural Resources, Division of Land and Water, is the signatory on this subdivision.
Request for Design Variance - Lot Dimensions.
Per VMC, the Planning & Zoning Commission is given the authority to grant waivers via the platting process.
VMC 16.04.060 Variances.
When, in the judgment of the commission, it would be inappropriate to apply literally a provision of this title the commission may waive or vary such provisions so that substantial justice may be done and the public interest secured; provided, that in no...