Title: South Harbor Basin Fuel Dock Feasibility Study - Draft Review
Attachments: 1. Updated DRAFT Return on Investment Analysis of a New Valdez Fuel Dock 2.22.21, 2. Dynamic ROI Valdez Tool Feb 1

ITEM TITLE: 

South Harbor Basin Fuel Dock Feasibility Study - Draft Review

 

SUBMITTED BY: Jeremy Talbott, Ports & Harbors Director

 

FISCAL NOTES: 

Expenditure Required: N/A

Unencumbered Balance: N/A

Funding Source: N/A

 

RECOMMENDATION:

Discussion Item Only: South Harbor Basin Fuel Dock Feasibility Study - Draft Review

 

SUMMARY STATEMENT:

During the 2020 capital projects, approval and budgeting process the City Council approved funding for a study on a potential fueling facility in the Commercial Boat Harbor.

In November of 2020, City staff selected Rain Coast Data through a professional services agreement for $31,550.00, to produce the attached draft documents.  Meilani Schivens from Rain Coast Data assembled a team of several industry professionals who have an in-depth knowledge of Valdez, waterfront construction, and community planning.  The Rain Coast Team analyzed three potential fuel dock owner operator scenarios:

                     Privately Constructed fuel dock facility with negotiated property and tideland leases from the City of Valdez,

                     A public private partnership with the City of Valdez constructing the facility and leasing out the operations to a private partner, and,

                     A facility operated and constructed by the City of Valdez.

This document is intended to be used as a tool to assist city administration, and elected officials determine if they wish to design, construct, and manage a potential fueling facility in the Commercial Boat Harbor.