ITEM TITLE:
Verbal Report: Harbor H-K Replacement Project Update
SUBMITTED BY: Nathan Duval, Assistant City Manager / Capital Facilities Director
FISCAL NOTES:
Expenditure Required: N/A
Unencumbered Balance: N/A
Funding Source: N/A
RECOMMENDATION:
Receive & File
SUMMARY STATEMENT:
Capital Facilities Director Nathan Duval will present Council with a project update on the H-K dock replacement project. The Tour Dock work is proceeding as scheduled but the H-K scope has experienced significant delays with supply chain and production of the floats. The City received final confirmation from the Contractor, Harris Sand & Gravel, that the work will not commence until the fall/winter to allow the materials to arrive and to minimize disruption during the extremely busy summer months at the harbor.