Change Order Report: Change Order with Harris Sand & Gravel for the Valdez SBH H-K Major Reconstruction project in the amount of $28,496.01
SUBMITTED BY: Austin Rake, Capital Facilities Project Manager
FISCAL NOTES:
Expenditure Required: $28,496.01
Unencumbered Balance: $1,972,991.86
Funding Source: 310-6441-58000
RECOMMENDATION:
Receive and file.
SUMMARY STATEMENT:
The remaining amount of the “Valdez SBH H-K Major Reconstruction” owner’s contingency of $407,609.31 will be used for the additional scope of work to fix the failing waterline outside of the Harbormaster office. The owner’s contingency is $28,496.01 short of the necessary remaining cost to complete the work and close the project.
This report is filed per City Procurement Code 2.80.050