ITEM TITLE:
Contract Amendment Report: Professional Services Agreement with DOWL, LLC for Construction Administration Services - Pavement Management Phase IV Meals Avenue
SUBMITTED BY: Brad Sontag Capital Facilities Project Manager
FISCAL NOTES:
Expenditure Required: N|A
Unencumbered Balance: N\A
Funding Source: N\A
RECOMMENDATION:
Receive & File
SUMMARY STATEMENT:
Click here to enter text.
DOWL, LLC contract amount will be increased by $38,965.00 for extra construction administrative services for Pavement Management Phase IV Meals Avenue.
Due to extended hours and days of work by the general contractor, DOWL’s field engineering costs increased to finish out the construction administration duties on site.
Please see attached DOWL, LLC proposal dated October 12, 2026, for a more detailed description of the additional scope of work.
This report is filed per City Procurement Code 2.80.050