Legislation Details

File #: 26-0240    Version: 1
Type: New Business Status: Agenda Ready
File created: 5/26/2026 In control: City Council
On agenda: 6/2/2026 Final action:
Title: Approval of Change Order with Knik Construction for Kelsey Dock Dolphin/Bollard Temp Install in the Amount of $70,500
Attachments: 1. Contract 2445 - Knik CO 2
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

ITEM TITLE: 

Approval of Change Order with Knik Construction for Kelsey Dock Dolphin/Bollard Temp Install in the Amount of $70,500

 

SUBMITTED BY: Kasey Walker, Capital Facilities Director

 

FISCAL NOTES: 

Expenditure Required: $70,500

Unencumbered Balance: $892,750

Funding Source: 310-9513-58010

 

RECOMMENDATION:

Approve the change order with Knik Construction for Kelsey Dock Dolphin/Bollard Temp Install in the amount of $70,500.

SUMMARY STATEMENT:

To improve the usability of the bollard placed in January, the old mooring dolphin and gangway must be removed. This operation includes removal of material above and below the water’s surface and will take place during the next optimal tide in mid-June.