ITEM TITLE:
Approval of Change Order with Knik Construction for Kelsey Dock Dolphin/Bollard Temp Install in the Amount of $70,500
SUBMITTED BY: Kasey Walker, Capital Facilities Director
FISCAL NOTES:
Expenditure Required: $70,500
Unencumbered Balance: $892,750
Funding Source: 310-9513-58010
RECOMMENDATION:
Approve the change order with Knik Construction for Kelsey Dock Dolphin/Bollard Temp Install in the amount of $70,500.
SUMMARY STATEMENT:
To improve the usability of the bollard placed in January, the old mooring dolphin and gangway must be removed. This operation includes removal of material above and below the water’s surface and will take place during the next optimal tide in mid-June.