ITEM TITLE:
Approval of Contract with Build Alaska General Contracting, LLC for VCT Causeway Repairs in the Amount of $518,205.00
SUBMITTED BY: Thomas Sanborn, Capital Facilities Project Manager
FISCAL NOTES:
Expenditure Required: $518,205.00
Unencumbered Balance: $750,000.00
Funding Source: 350-0310-55000.2011
RECOMMENDATION:
Approve the Contract with Build Alaska General Contracting, LLC for VCT Causeway Repairs in the Amount of $518,205.00
SUMMARY STATEMENT:
Project Description: This project includes repairs to eight (8) pile caps suffering from varying degrees of deterioration; as well as replacement of the guardrail spanning the full length of the causeway.
The remaining pile caps identified in the 2015 condition assessment from Moffat & Nichol will be repaired in this project. These repairs will stop further deterioration of the concrete piles and therefore extend the useful lifetime of the causeway.
Construction Schedule: The Contractor has between May 1, 2021 and July 2, 2021 to complete the work for this project.
Liquidated Damages: $500 per day.
Bidding: Two responsive bids were received by the bid opening deadline for this project. There were no non-responsive bids for this project. Build Alaska General Contracting, LLC was the low bid, and was approximately 14% below the Engineer’s Estimate.
Engineer’s Estimate: $600,000.00