ITEM TITLE:
Change Order Report: Contract with Harris Sand & Gravel for Pavement Management Phase 1 - West Egan Drive.
SUBMITTED BY: Thomas Sanborn, Capital Facilities Project Manager
FISCAL NOTES:
Expenditure Required: $17,892.00
Unencumbered Balance: $4,814,668.65
Funding Source: 310-1200-58000
RECOMMENDATION:
Receive & File
SUMMARY STATEMENT:
Change Order 1 adds the replacement of a 12-inch water main valve and deducts the work for a 6-inch water valve replacement from the contract. This need was clarified by the City of Valdez Water Department following a site walkthrough.
The total cost for this change order, included deductive savings, is $17,892.
This report is filed per City Procurement Code 2.80.050