Title: Approval of Contract Amendment #19 to R&M Consultants, Inc. for the New Boat Harbor Phase 2 Engineering Services and Inspections in the Amount of $1,042,135.00
Attachments: 1. R&M Contract Amendment #19.pdf, 2. Attorney Pre-approval R&M CA #19.pdf

ITEM TITLE: 

Approval of Contract Amendment #19 to R&M Consultants, Inc. for the New Boat Harbor Phase 2 Engineering Services and Inspections in the Amount of $1,042,135.00

 

SUBMITTED BY: Laura Langdon, Project Manager

 

FISCAL NOTES: 

Expenditure Required: $1,042,135.00

Unencumbered Balance: $5,858,025.08

Funding Source: Original #310-6450-58444; Current #310-6450-58000 New Harbor Planning.

 

RECOMMENDATION:

Approve contract amendment #19 to R&M Consultants, Inc. for the new boat harbor phase 2 engineering services and inspections in the amount of $1,042,135.00.

 

SUMMARY STATEMENT:

This amendment comes for approval because it is recommended to maintain continuity with the engineering and project management firms from phase 1 to phase 2.

The construction contract to Pacific Pile and Marine for phase 2 is underway.

 

R&M along with Arcadis are currently working through project coordination and submittal review.

 

Engineering support and construction inspections for the remainder of phase 2 are proposed to follow the current construction schedule provided by the construction contractor, Pacific Pile and Marine which extend to December of 2018.

R&M and Arcadis will be coordinating together throughout phase 2. Below summarize their tasks:

 

R&M

•                     Attend monthly Executive meetings.

•                     Complete a conformed set of documents.

•                     Attend USACE weekly meetings.

•                     Review submittals and respond to RFIs.

•                     Daily observation during key construction activities the summer of 2017 and bi-weekly inspections for the remainder of work.

•                     Inspections of buildings, pile driving, floats, float utilities, transfer bridge, and bilge treatment system.

•                     Special material inspections and lab testing.

•                     State Fire Marshal permitting.

•                     Substantial and final completion inspections.

•                     Prepare as-builts.

 

Arcadis

•                     Run and facilitate monthly Executive meetings including Ports and Harbor Commission meetings and City Council.

•                     Conduct weekly construction meetings.

•                     Monitor progress, costs, and schedule.

•                     Coordination with the USACE.

•                     Inspection assistance to R&M.

•                     Review payment applications.

•                     Monitor submittals and RFIs.

•                     Review cost proposals and change orders.

•                     Close out services including punch lists, final accounting, and commissioning.